Release churn five-whys v0.70.0–v0.71.1 + retire 'freeze main to tag' (cut at fixed sha in own worktree) #5185

Open

Description

@noahgift

Ask

The release train keeps freezing main and then taking days to release. This ticket has two deliverables.

1. Five-whys with measured numbers, v0.70.0 through v0.71.1. For each release, record:

  • freeze start;
  • cut, tag and publish times;
  • hours main was frozen;
  • every red hit on the release path, and whether that step had ever been green.

2. A planted C314 quorum round on retiring the "freeze main to tag" rule. The proposed replacement:

  • no freeze;
  • every release is cut at a fixed sha in its own worktree;
  • a red there means the fix lands on main the normal way, and the next cut picks it up.

This is a gate change, so a non-author sign-off round applies before it is adopted.

Acceptance

  • Timeline table, with a source for every number (git, GitHub API or the release log).
  • Five-whys down to a root cause.
  • Quorum receipt: verdict, planted fact caught, conditions.

🤖 Generated with Claude Code

Activity

  1. added this to the 0.71.1 milestone on Oct 12, 2026
  2. noahgift commented on Oct 12, 2026

    @noahgift
    ContributorAuthor

    Five whys: why a frozen release branch takes days (measured; a3)

    release freeze→tag (h) reds on the release path never-green reds
    v0.70.0 129.57 4 2
    v0.70.1 21.24 5 3
    v0.70.2 8.79 7 2
    v0.70.3 17.04 4 2
    v0.71.0 7.74 10 1

    Main was frozen about 86 h of 354 h (24%). The best freeze→tag so far, 7.74 h, is 10× the 45-minute rule.

    1. Why days? Every red inside the window costs a full loop: cut a fix PR, merge it through the queue, re-run. There were 30 reds across 5 releases.
    2. Why are there reds in the window? The window runs long computations (model smoke 58.5 min, publish dry-run 14.5 min) for the first time on the cut sha.
    3. Why do they go red there? 10 of the 30 reds came from steps that had never been green. A step that has never passed can only stop a window.
    4. Why is that allowed? The release path had no rule that a step must have a last green and a measured time.
    5. Root cause: the release window does computation and discovery instead of checking receipts.

    0.71.1, measured: models 3625 s (GO). A missing release-notes input then stopped the train for 1073 s. That is 78 min before the tag, already over budget.

    The fix (owner a3, effective 0.71.2):

    • The nightly job runs the models smoke and the publish dry-run on the candidate sha and writes a receipt keyed by sha.
    • The window only checks that a receipt exists for the exact cut sha. If not, it STOPs; it never re-runs.
    • An inputs check runs before the cut: release notes and receipts must exist, or the window doesn't open.
    • The window prints elapsed time per step and an andon line past 45 min.
    • Never-green steps go to LAB.

    The budget comes to tag 0.2 + clean-room 25.7 + assets check 0.1 ≈ 26 min, which leaves about 19 min for publish through close. This is a gate change, so it needs a non-author C314 sign-off and 2 reviews.

    🤖 Generated with Claude Code

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

No one assigned

    Labels

    No labels
    No labels

    Type

    No type

    Projects

    No projects

      Relationships

      None yet

      Development

      No branches or pull requests

      Issue actions