The cross-repo contract register

Four obligations, and they are the whole cross-repo contract. Everything else in either repo's plan is internal. This file exists for one reason, stated in station's station-and-plugin-plan.md §8: so that C1 through C4 have somewhere to be visibly outstanding, which is the only property that makes a cross-repo obligation different from a good intention.

A row changes in the same commit that changes its state. DONE means merged, in whichever repo owes it — never "written", never "on a branch". A row citing another repo is updated when the change merges there, naming the PR.

States: NOT STARTED, IN PROGRESS (a PR is open), DONE (merged), BLOCKED (waiting on work outside this item, named in the note).

The register

# owed by to what due state discharged by
C1 plugin station ref and config corpus sections, as pure data before station Stage 2 — earlier than P1's exit DONE #7ref 97 entries, config 86, both pure. Delivered ahead of station Stage 2, which was the point.
C2 plugin station lifecycle and order corpus sections plus the draft language-neutral driver contract in DOCS.md (§15.2 — probes, command vocabulary, canonical observable) before P1's exit DONE #7 — 53 entries + DOCS.md §4, landed together because a driver section without its contract is not shippable.
C3 station plugin a working Stages 2–3b implementation to extract from, and its own suites as the bar before plugin P3 DONE voxgig/station#9 — Stages 2, 3 and 3b, 11/11 ports green — merged as f7656aa; review follow-ups in voxgig/station#10 (2036cd6). P3 is unblocked.
C4a station plugin conformance on the pure sections: station runs C1's ref and config against its own implementation and reports divergence as a plugin issue rather than absorbing it continuous from Stage 2 NOT STARTED — the wiring is in flight: station is landing a plugin-corpus conformance suite in its own test suite (2026-08-24). This row turns DONE when that suite merges and runs in station's CI.
C4b station plugin the same for C2's lifecycle and order continuous from Stage 3b NOT STARTED — same wiring, same suite (2026-08-24); station's feature.test.ts already holds its resolver to plugin's order semantics by construction, but that is not the corpus running.

What each row is actually for

C1 is the tightest, and it is the one that goes wrong quietly. Station's Stage 1 lands the ref grammar and Stage 2 lands the identity change. If ref arrives after Stage 2, station has already written ref parsing and the corpus becomes a retrofit audit rather than a contract — it will be read to confirm what was built instead of to constrain it. Both sections are pure data (§15.3), so the files are the deliverable: this is cheap for plugin, and only cheap if it is early. That is why C1 is owed before P1's own exit rather than at it.

C2 cannot ship as corpus files alone. lifecycle and order are driver sections (§15.3), so a port cannot run them without the command vocabulary they are written against. Adding either without the DOCS.md contract in the same change produces a suite no port but the canonical can implement.

C3 is what stops P3 being a thought experiment. Plugin's extraction bar is station's own integration test — twenty-plus declared instances with none constructed at open(), two instances of one api with distinct placeholders, and a fleet-wide feature default reaching an instance that never mentions it. The last of those is Stage 3b work, which is why P3 gates on 3b and not on Stage 3.

C4 is the one nothing forces. It is split because its two halves become runnable at different moments, but the real point is that nothing fails when a team stops running another repo's corpus. The mitigation is not diligence: it is making plugin's corpus part of station's own CI from Stage 2, so drift is red rather than unnoticed. Until that wiring exists, C4 is an intention with a row.

Standing note

The build-natively decision — station implements plugin's semantics in its own ports rather than depending on the library — is what makes these four the entire contract. It also makes them the only thing preventing the drift that decision buys. A DONE on C1 and C2 with C4 still NOT STARTED is the shape of two repos agreeing on paper and diverging in code.